REI Expo 2026: Solar & BESS Manufacturing take Centre Stage

Renewable Energy India Expo (REI Expo – 19th edition) was held from 22nd October to 24th October, 2026 at India Expo Centre in Greater Noida. The show was organised by Informa Markets, and the three-day event brought together 1,251 brands and 65,133 trade visitors.
REI Expo 2026 was co-located with the fourth edition of The Battery Show, which focused on expansion and new launches of energy storage solutions.
Solar Manufacturers Step Up Capacity, Backward Integration
The team of CableCommunity team visited the expo and observed a strong focus on capacity expansion, backward integration and energy-storage manufacturing. The exhibitors displayed their existing solar panels and discussed plans to expand manufacturing capacities and set up new plants.
True Power to Enter Solar Panel Manufacturing

True Power Limited, a Lucknow-based manufacturer of earthing products and cables, is about to enter the solar panel manufacturing business. While speaking with the team of CableCommunity, Mr. Akshay Kumar Singh, General Manager of the company, said that True Power is setting up a new plant for manufacturing solar panels in Lucknow. He further added that the plant will be developed on a 150-acre site and is expected to be commissioned in January or February 2027.
The company has also expanded its product portfolio with the launch of a 1.1 KW solar Balance of System (BoS) kit. The BOS kit refers to all the essential components required to complete a solar power installation apart from the solar panels themselves. These components support safe generation, conversion, transmission, monitoring, and distribution of solar energy.
Emmvee to Expand Module, Ingot and Wafer Manufacturing Capacity

Emmvee Group discussed its plans to expand its solar module and cell manufacturing capacities.
The company currently has a solar module manufacturing capacity of 10.3 GW, which is expected to increase to 16.3 GW by December 2026. Further, solar cell manufacturing capacity will be expanded from the current 2.9 GW to 8.9 GW by March 2027. For this, Emmvee is setting up a new plant in Karnataka with an investment of ₹5,500 crore.
As a part of backward integration, the company will also set up a 9 GW ingot and wafer manufacturing facility, for which the location has not yet been finalised. The facility will be commissioned in two phases, with 5 GW scheduled for FY29 and the remaining 4 GW for FY30. The total capital expenditure for the project is estimated at ₹ 5,000–5,500 crore.
Gautam Solar to invest ₹4,000 Cr for Cell, Ingot and Wafer Manufacturing

Gautam Solar outlined its plans to establish a solar cell, ingot, and wafer manufacturing plant in Madhya Pradesh with an investment of ₹4,000 crore.
At the REI expo, a representative of the company mentioned that the upcoming facility will support backward integration for Gautam Solar’s existing solar module manufacturing plants in Bhiwani and Haridwar.
The new plant will be developed in phases, with the first phase covering solar cell manufacturing and the second phase adding ingot and wafer manufacturing lines.
At the expo, Gautam Solar also displayed other products, including distribution boxes, inverters, Battery Energy Storage Systems (BESS), and a 640 Wp solar module launched at the previous edition of the event.
Saatvik Launches 640 Wp Solar Module

Saatvik Green Energy Ltd., an Indian renewable energy company headquartered in Gurugram, launched 640 Wp G12 R TOPCon solar module at REI Expo 2026. The module has an efficiency of 23.69% and features 132 rectangular solar cells.
These newly launched modules are being manufactured at the company’s plant in Odisha, and Saatvik expects to begin supplying them in November 2026.
Saatvik Green Energy is targeting a solar module manufacturing capacity of 8.8 GW by the end of FY27, up from the current capacity of 4.8 GW.
Also, the company will be entering the energy storage segment next year. According to a company spokesperson, Saatvik will manufacture BESS at its plant in Ambala.
Inox Solar Targets Jan 2027 for Solar Cell Production

Inox Solar is setting up a solar cell, ingot, and wafer manufacturing plant in Odisha. The solar cell manufacturing line is expected to be commissioned by January 2027, while the ingot and wafer manufacturing lines are scheduled to be commissioned over the next two years.
Further, the company will also be foraying into inverter and BESS manufacturing segment in 2027. Speaking with CableCommunity, a company representative said that Inox Solar will establish a new plant for manufacturing inverters and energy storage systems. However, the location for the plant has not been finalised, although Gujarat is being considered.
BESS Manufacturing and Storage Technologies Gain Ground at REI 2026
Raydean Showcases Ray-Batt Storage System, Microinverters

Raydean Enterprises Limited, a Jaipur-based manufacturer of renewable energy equipment, showcased its recently launched Energy Storage System and microinverters at the expo.
Mr. Praveen Mishra, Senior Manager at Raydean Enterprises, told the team of CableCommunity that the Energy Storage System, namely Ray-Batt, includes a lithium-based energy storage system with a storage capacity of up to 50 kWh. This system is available in rack-mounted, wall-mounted, and wheeled lithium battery configurations to fit in different installation spaces.
Further, the company’s newly launched microinverters are available in 1 KW and 2 KW power output capacities. These solar microinverters are specifically designed for balcony power plants and residential rooftop systems. Raydean is also developing hybrid inverters with an output capacity of up to 10 KW.
Waaree Commissions ₹8,000 Crore BESS Manufacturing Plant

Waaree Group has recently commissioned a new BESS container manufacturing plant in Gujarat with a total annual capacity of 5.15 GWh. This marks the first phase of the company’s plan to reach 20 GWh of storage capacity, a plan backed by an investment of ₹8,000 crore.
In a conversation with CableCommunity, a company representative discussed Waaree’s expansion beyond solar and BESS manufacturing. The representative added that Waaree is exploring opportunities in semiconductor manufacturing and green hydrogen, although further details have not yet been disclosed.
Additionally, Waaree has also recently acquired a stake in a smart meter manufacturing company based in Greater Noida.
Vikram Solar Targets LFP Cell Manufacturing by FY29

Vikram Solar, a Kolkata-based solar energy company, displayed its 650 Wp, 670 Wp, and 720 Wp solar modules at REI Expo 2026.
During the REI Expo 2026, the company representative told CableCommunity that Vikram Solar will be entering Lithium Iron Phosphate (LFP) cell manufacturing by FY29.
The manufacturing of LFP cells will be undertaken by a subsidiary of Vikram Solar, VSL PowerHive. The subsidiary company is setting up a 7.5 GWh Battery Energy Storage System assembly plant in Oragadam near Chennai, Tamil Nadu, which is expected to be inaugurated in January 2027. This plant will initially assemble imported LFP cells, and by FY29 the company will begin backward integration after starting production at its LFP cell production line.
Premier Energies to Set up 12 GWh BESS Plant in Telangana

Premier Energies will develop a 12 GWh BESS manufacturing plant in Telangana in partnership with RCT Nexor Energy, a subsidiary of Germany-based RCT Group.
The announcement was shared by Mr. Shivesh Mishra, Senior Manager at Premier Energies, during the expo. The plant will be developed in two phases and is expected to begin commercial operations by June 2027. The company has not disclosed the investment required for the project.
Premier Energies is also planning new product launches and manufacturing expansions for FY28. These include the launch of aluminium frames and the development of an ingot and wafer manufacturing facility.
REI 2026 Signals Shift Towards Integrated RE Manufacturing
REI Expo 2026 reflected a widening of India’s domestic renewable-energy manufacturing ambitions. While solar module capacity continues to expand, manufacturers are increasingly moving towards backward integration into cells, ingots and wafers, alongside investments in BESS and battery-cell manufacturing. The announcements indicate an industry moving towards a more integrated domestic renewable-energy supply chain
Also, the expo has been renewed for its next edition (20th edition), which will be held on 4th to 6th November 2027 at the India Expo Mart, Greater Noida.