JSW Infra. Receives LoA for Constructing Multi-Modal Cargo Terminal in TN

JSW Infrastructure Limited has received a Letter of Award (LoA) to construct Gati Shakti Multi-Modal Cargo Terminal (GCT) at Arakkonam, Tamil Nadu. This contract was secured from the Chennai Division of Southern Railway, as per JSW Infrastructure’s stock filing dated June 27, 2024.

Scope of work in this project includes construction and operation of the Gati Shakti Multi-Modal Cargo Terminal on railway land at Arakkonam. The railway land for this project will be licensed for a period of 35 years. JSW Infra. shall begin work on this terminal within 3 months from securing requisite construction approval. Following this, construction of the cargo terminal is expected to be completed in a period of 18 months.